NEW QUESTION # 10
Which of the following is a prerequisite for using Automated Receipt Settlement (ERS) in a procurement process? Note: There are 2 correct answers to this question.
- A. The indicator for ERS is set in the purchasing info record.
- B. The indicator for ERS is set in the material master record.
- C. The indicator for ERS is set in the supplier master record.
- D. The indicator for ERS is set in the purchase order item.
Answer: C,D
NEW QUESTION # 11
What happens when you create a stock transport order with the specific order type for stock transport order with outbound delivery? Note: There are 2 correct answers to this question.
- A. You are prompted to manually input all required shipping information.
- B. The system automatically determines the shipping data based on master data and configuration.
- C. A Shipping tab appears in the item details of the stock transport order.
- D. You are automatically redirected to the Manage Outbound Deliveries app.
Answer: B,C
NEW QUESTION # 12
Where can you specify the rule to automatically determine the picking location in the outbound delivery item?
- A. In the configuration of the delivery type
- B. In the configuration of the delivery item category
- C. In the plant data of the material master record
- D. In the detailed configuration of the shipping point
Answer: A
NEW QUESTION # 13
Which steps are required for data load preparation? Note: There are 3 correct answers to this question.
- A. Design programs or reports required to extract data and initiate data cleansing
- B. Perform full data load to determine the required loading times
- C. Determine data requirements based on scenario reviews
- D. Review data load templates and determine data mapping
- E. Determine if public or private cloud is required for data migration
Answer: A,C,D
NEW QUESTION # 14
What are key activities of the Prepare phase of the SAP Activate methodology? Note: There are 3 correct answers to this question.
- A. User training
- B. Starter system provisioning
- C. Project setup
- D. Data migration
- E. Customer self-enablement
Answer: B,C,E
NEW QUESTION # 15
Which of the following process steps update the stock in transit? Note: There are 2 correct answers to this question.
- A. Post a goods receipt for a stock transport order
- B. Create a delivery for a stock transport order
- C. Post a stock transfer in two steps
- D. Post a goods issue for a stock transport order
Answer: A,D
NEW QUESTION # 16
Which of the following reference documents can you use to plan and post a goods movement? Note:
There are 3 correct answers to this question.
- A. A reservation
- B. A purchase requisition
- C. A production order
- D. A purchase order
- E. An accounting document
Answer: A,C,D
NEW QUESTION # 17
Where do you enable a customer-specific field to be available for UIs and reports relevant for the same business context?
- A. In the Maintain SAP Business Technology Platform Extensions app
- B. In the Extensibility Cockpit app
- C. In the Custom Fields and Logic app
- D. In the Runtime Authoring mode
Answer: C
NEW QUESTION # 18
In case of a delivery without reference to a sales order, what are the prerequisites for a successful batch determination? Note: There are 2 correct answers to this question.
- A. Assign the delivery type to a batch search procedure
- B. Assign the default order type to a batch search procedure
- C. Assign a default order type to the delivery item category
- D. Assign a default order type to the delivery type
Answer: B,D
NEW QUESTION # 19
When can you add relationships in the organizational structure in SAP Central Business Configuration?
Note: There are 2 correct answers to this question.
- A. After content activation
- B. Before initial content activation
- C. Before defining the primary finance settings
- D. During content activation
Answer: A,B
NEW QUESTION # 20
What is the purpose of the Starter system in the SAP S/4HANA Cloud implementation project?
- A. To configure the customer's personalized solution for demonstration and testing during the Realize phase
- B. To demonstrate SAP Best Practices processes in a preconfigured system and identify customer personalization requirements
- C. To demonstrate the customer's personalized solution, including process flows, the organizational structure, and authorizations
- D. To conduct a blueprint workshop to identify all customer requirements for a completely customized solution
Answer: B
NEW QUESTION # 21
You create a purchase order that requires an inbound delivery. Which field must you fill in?
- A. The QA control key
- B. Goods Receipt Indicator
- C. Confirmation Control Key
- D. Purchasing Value Key
Answer: C
NEW QUESTION # 22
In what phase of the SAP Activate methodology do you test the business processes?
- A. Realize
- B. Prepare
- C. Explore
- D. Deploy
Answer: A
NEW QUESTION # 23
Which of the following are features of Inventory Management? Note: There are 3 correct answers to this question.
- A. Special stocks management
- B. Storage types management
- C. Stock management at bin level
- D. Stock types management
- E. Stock value management
Answer: A,D,E
NEW QUESTION # 24
Where can you maintain custom texts that specific users receive per notification when a situation arises?
- A. In a Custom Communication Scenario
- B. In a Situation Type
- C. In a Situation Template
- D. In a Custom Logic
Answer: C
NEW QUESTION # 25
What needs to be activated as a prerequisite for using a product allocation check? Note: There are 2 correct answers to this question.
- A. The availability check against product allocation for basic Available-to-Promise
- B. The availability check against product allocation per client
- C. The availability check against product allocation in Sales and Distribution
- D. The availability check against product allocation in the context of aATP
Answer: B,D
NEW QUESTION # 26
What can you use the View Browser app to do?
- A. Display custom SAP views irrespective of draft or released status
- B. Launch analytic cloud stories
- C. Get a list of all available analytical CDS views and their artifacts
- D. Create, edit, and delete CDS views
Answer: C
NEW QUESTION # 27
How do you specify whether a material should be serialized?
- A. You create an equipment master record for each individual piece of the material
- B. You must first define the material as batch managed and then create serial numbers
- C. In configuration, you assign a serial number profile to the material type
- D. You enter a serial number profile in the material master record at plant level
Answer: D
NEW QUESTION # 28
......