NEW QUESTION # 48
How does agile address the risk associated with the project not being fully understood at the beginning?

  • A. By allowing a lot of detail at the start
  • B. By avoiding too much detail at the start
  • C. By requiring details at the start
  • D. By preventing the analysis of details at the start

Answer: D


NEW QUESTION # 49
Which is a typical characteristic of 'business as usual' work?

  • A. It is delivered by a temporary team
  • B. It is delivered by an established team
  • C. It requires a specific dedicated project manager
  • D. It is executed by program management

Answer: B


NEW QUESTION # 50
What is typically displayed on a board to show progress to people working on a project?

  • A. Product backlog
  • B. Information radiator
  • C. User story
  • D. Agilometer assessment

Answer: B


NEW QUESTION # 51
Which two statements about tailoring the business case in an agile environment are CORRECT?
1. It should be unnecessary because products of the highest value will be delivered first.
2. It should identify the minimum viable product and when it will be delivered.
3. It should take into account that the scope may be reduced during the course of the project.
4. It should show the features, the order in which they will be delivered and any dependencies.

  • A. 2 and 3
  • B. 1 and 2
  • C. 3 and 4
  • D. 1 and 4

Answer: A


NEW QUESTION # 52
Which statement is CORRECT with respect to the management of risk using PRINCE2 Agile?

  • A. It should always be carried out formally
  • B. It should always be addressed during the daily stand-ups
  • C. It should always be appropriate to the needs of the project
  • D. It should always be carried out informally

Answer: C


NEW QUESTION # 53
Which is an advantage of frequent releases?

  • A. Releases can be used to replace management stages
  • B. Configuration management becomes less important
  • C. The delivery team becomes more experienced at product handover
  • D. A 'one-team' culture in the project team is encouraged

Answer: C


NEW QUESTION # 54
Which statement about the 'keep teams stable' target is CORRECT?

  • A. It is the primary reason why the tolerance for cost is set to zero
  • B. It results in the early delivery of a minimum viable product
  • C. It applies primarily to the long term, such as a project or a program
  • D. It prevents compromising the overall quality level of the product

Answer: A


NEW QUESTION # 55
Which statement about the 'directing a project' process is CORRECT?

  • A. A project board member should fulfill the product owner role within a delivery team
  • B. The project board should increase the stage-level time tolerance
  • C. The project board should attend regular project progress meetings
  • D. The project board should make decisions based on the Agilometer risks

Answer: A


NEW QUESTION # 56
Which statement about the 'embrace change' target is CORRECT?

  • A. It minimizes the time needed to train a new team member
  • B. It encourages the customer to raise new ideas
  • C. It reduces testing in order to meet deadlines
  • D. It reduces the planning of dependencies between projects

Answer: B


NEW QUESTION # 57
Which is a purpose of the 'controlling stage' process?

  • A. To report stage progress to the project board
  • B. To execute and deliver the project product
  • C. To draft the plan for the next stage's work
  • D. To establish whether the project is complete

Answer: A

Explanation:
Reference:
%20remains%20within%20tolerance.&text=Risks%20and%20issues%20are%20kept%20under%20control


NEW QUESTION # 58
Which TWO project board responsibilities are specifically assigned to the senior user?
1) Demonstrating the achievement of benefits.
2) Specifying the needs of those impacted by the outputs.
3) Balancing business, user and supplier demands.
4) Ensuring that the project delivers value for money.

  • A. 2 and 3
  • B. 1 and 2
  • C. 3 and 4
  • D. 1 and 4

Answer: B


NEW QUESTION # 59
Which is a reason for releasing a product into a staging area?

  • A. It enables the faster delivery of changes
  • B. It supports management by exception
  • C. It supports regulatory compliance checking
  • D. It enables a phased Waterfall approach

Answer: C

Explanation:
Reference:
%20and%20verification%20process


NEW QUESTION # 60
How should product-based planning be used as part of PRINCE2 Agile?

  • A. To plan by focusing on the features required
  • B. To track progress against the team plan
  • C. To enable team planning to be predictive
  • D. To create the project plan using empiricism

Answer: A


NEW QUESTION # 61
Which statement about the waterfall methodology definition is CORRECT?

  • A. It promotes the use of experiments carried out in a scientific way
  • B. It states that deadlines should not be moved
  • C. It has distinct goals for each stage of development
  • D. It is a behavior that involves making things transparent

Answer: C


NEW QUESTION # 62
Which process can take place during a release review workshop?

  • A. Controlling a stage
  • B. Managing a stage boundary
  • C. Directing a project
  • D. Managing product delivery

Answer: D


NEW QUESTION # 63
When tailoring the plans theme in an agile environment, what is recommended about using a Gantt chart?

  • A. It should be used when planning at the project level
  • B. It should be used when planning at the delivery level
  • C. It should be used when controlling the quality of the products delivered
  • D. It should be used when monitoring the amount of products delivered

Answer: A


NEW QUESTION # 64
Which is often used during a retrospective to capture lessons?

  • A. A Gantt chart
  • B. A burn chart
  • C. A Glad! Sad! Mad! board
  • D. A Kanban board

Answer: C


NEW QUESTION # 65
During which process should release planning be done for the FIRST time?

  • A. Managing product delivery
  • B. Controlling a stage
  • C. Initiating a project
  • D. Managing a stage boundary

Answer: D


NEW QUESTION # 66
Which statement about the 'accept that the customer doesn't need everything' target is correct?

  • A. It can result in the early delivery of a minimum viable product
  • B. It gives confidence on the progress of the project
  • C. It allows misunderstandings to be dealt with appropriately
  • D. It is achieved by managing the culture of the team carefully

Answer: C